top of page

PJM's 2028/29 BRA: $325/MW-day price cap

  • Jul 16
  • 6 min read

PJM’s 2028/29 Base Residual Auction, announced on July 14, 2026, cleared lower than the prior auction while its supply shortfall widened. The lower price traces to the temporary cap; the widening shortfall reflects fundamentals the capped price does not express.

Takeaways:

  • PJM's 2028/29 Base Residual Auction cleared at a single RTO-wide $325/MW-day — the third consecutive auction at the FERC-approved cap.

  • Number of constrained LDAs remained at zero, and there was no LDA-level breakout

  • 138.3 GW of UCAP ($16.4 billion) while falling 6.8 GW short of the reliability requirement.

  • Price was set by a temporary cap and floor in place since 2025, not by market conditions; the 2.5% decline from the prior auction reflects only a change in the reference resource's accreditation factor (0.77 to 0.79).

  • PJM's own uncapped simulation puts the clearing price 71% above the applied cap — up from 18% two auctions ago — implying the collar reduced the auction's cleared value by approximately $13.3 billion.

  • The collar covers four auctions through 2029/30; the last authorized auction runs in December 2026, after which the cap reverts to a Net CONE-based figure PJM estimates at approximately $550/MW-day.

  • Forward indicators show no movement toward a sub-cap outcome: new generation and uprates have declined across the three capped auctions (2,669, 774, 525 MW), and a third consecutive auction clearing more than one percentage point below the reserve margin would require PJM to conduct a Reliability Backstop Auction.

Auction results


The reserve margin of 14.7% includes the 10,864 MW committed under Fixed Resource Requirement plans rather than cleared in the auction. PJM also reported that the RTO as a whole failed its market structure test — the three pivotal supplier test — resulting in offer mitigation for all existing generation capacity resources.


Metric

2028/29 BRA

Clearing price (RTO, all LDAs)

$325.00/MW-day UCAP — at cap, −2.5%

Cleared UCAP

138,318 MW

FRR committed

10,864 MW

Shortfall vs. reliability requirement

6,831 MW

Reserve margin

14.7%

Cleared value

$16.4 billion

New generation and uprates

525 MW




The clearing price declined while the supply shortfall widened. The price follows from the cap; the widening shortfall reflects supply-demand fundamentals that the capped price does not express. The sections below review the cap's origin, its duration, its calculation, and the indicators that would signal a change.



Origin and expiry


The mechanism is a price cap and floor, or collar, and it is temporary rather than a standing feature of PJM’s market design. The cap has bound in every auction so far; the floor has not.


Date

Event

December 30, 2024

Governor Shapiro and the Commonwealth of Pennsylvania file a complaint at FERC

January 2025

PJM and the Commonwealth settle

February 2025

PJM files conforming tariff revisions

April 21, 2025

FERC approves 4-0, covering two auctions

July 2025

2026/27, the first auction under the cap, clears at $329.17

December 2025

2027/28 clears at $333.44

February 2026

PJM Board moves to extend; files February 27

April 28, 2026

FERC approves the extension, covering four auctions

July 14, 2026

2028/29 clears at $325.00

December 2026

2029/30 — the last auction under the current authorization

2030/31

Reverts to PJM’s standard VRR curve unless extended again


The cap originates in litigation, not in PJM’s market design. The 2025/26 auction cleared at $269.92/MW-day, more than nine times the $28.92 of the year before. In December 2024, Governor Josh Shapiro and the Commonwealth of Pennsylvania filed a complaint at FERC arguing that the standard price cap — which had just been raised to the greater of the gross cost of new entry or 1.75 times the net cost — was unjust and unreasonable, and asking that it be set at no more than 1.5 times net cost of new entry. PJM settled rather than litigate, and the negotiated cap and floor is what emerged. Other PJM-state governors and the Organization of PJM States supported the complaint; PJM’s Independent Market Monitor, LS Power and others opposed the settlement filing filed a complaint at FERC.


The PJM Board moved to extend the cap in February 2026, and FERC approved the extension that April. One auction remains under it. Absent a further extension, the cap reverts to PJM’s standard VRR curve — a multiple of Net Cost of New Entry rather than a negotiated figure, which PJM’s February 2026 filing estimated at roughly $550/MW-day with a zero floor.


How the cap is calculated


The cap is anchored in installed capacity (ICAP) terms at a fixed $256.75/MW-day. RPM clears and settles in unforced capacity (UCAP) terms. To translate between them, PJM divides the ICAP-denominated cap by the accreditation factor of its reference resource, a dual-fuel combustion turbine. PJM describes the method in its results release: the cap “is calculated using the accredited capacity of the PJM reference resource.”


The calculation has two inputs. One is fixed; the other is reset each auction.

Applied cap (UCAP)   =   ICAP anchor   ÷   AUCAP factor

2028/29:   $325.00   =   $256.75   ÷   0.79

Auction

ICAP anchor

÷  AUCAP factor

=  Applied cap (UCAP)

2026/27

$256.75/MW-day

0.78

$329.17/MW-day

2027/28

$256.75/MW-day

0.77

$333.44/MW-day

2028/29

$256.75/MW-day

0.79

$325.00/MW-day

ICAP anchor: the cap fixed in installed-capacity terms under the settlement; unchanged across auctions.   AUCAP factor: the reference resource's accredited unforced capacity as a share of its installed capacity; reset each auction.

The anchor is identical in all three auctions. Only the AUCAP factor moves. It rose from 0.77 to 0.79 for the 2028/29 auction, which lowered the applied cap by 2.5%. Supply and demand conditions were not a factor in the decline, and the factor can move in either direction independent of market fundamentals.


The floor is derived the same way. For the 2027/28 auction it was $138.25/MW-ICAP, or $179.55/MW-day UCAP.


Indicators for future auctions

An auction clears below its ceiling when the supply curve shifts far enough right to intersect demand below the cap. PJM publishes a simulation of each auction with no cap or floor applied. That simulation indicates the distance between the applied price and an unconstrained outcome.



The premium is not uniform across the footprint. In the constrained ComEd zone the 2028/29 simulation implies roughly 139%, and an uncapped auction would have totaled $29.7 billion against the actual $16.4 billion.


Closing that distance requires a sustained increase in cleared supply or a downward revision to forecast load. Supply-side movement has been limited:


  • Cleared capacity rose 3,733 MW, of which 525 MW was new generation and uprates.

  • Natural gas gained 5,639 MW UCAP — mostly higher accredited UCAP factors, coal-to-gas conversions, and units absent from the prior auction. Coal declined 2,941 MW.

  • Physical supply across the footprint grew 1,294 MW ICAP, against a forecast peak roughly 2,000 MW higher.


This was the second consecutive auction to clear more than one percentage point below the installed reserve margin; under PJM’s tariff, a third would require PJM to conduct a Reliability


Backstop Auction. PJM has opened two fast-track stakeholder processes in response, covering large-load additions and backstop procurement.


What to monitor


Signal

Where it appears

Indication of a sub-cap outcome

Simulated uncapped price

PJM auction release and BRA report

Declining in successive auctions toward the applied cap.

New generation and uprates

BRA report

Sustained multi-thousand-MW entry, reversing the 2,669 → 774 → 525 MW decline.

Expedited Interconnection Track

PJM queue reporting

Projects reaching commercial operation. Up to 10 state-sponsored projects a year; sunsets end-2027.

Backstop Procurement

September 2026 bid window, pending FERC filing

Volume procured, and cost allocation. PJM has said allocation will follow state preferences.

Load forecast revisions

PJM annual load report

Downward revisions to large-load additions, or rules excluding unserved data center load.

Reference resource accreditation

Planning Period Parameters

Moves the applied ceiling independent of supply and demand.


The collar's expiry is a scheduled event. If supply conditions are unchanged at that point, the applied cap reverts to the Net CONE-based figure and the constraint on the clearing price is removed.


Implications


Under the cap, the clearing price reflects a negotiated ICAP anchor divided by a reference-resource accreditation factor. It is not a measure of what supply costs.


Two consequences follow for market participants in the PJM footprint. Capacity revenue is administratively bounded for the duration of the cap, and the applied ceiling moves for reasons unrelated to any individual asset. Resource adequacy is also being addressed increasingly outside the auction. PJM has cited a Reliability Backstop Procurement targeted for September, “Connect and Manage” frameworks for large loads, an Expedited Interconnection Track, and a June 9 RFP, administered by CRA, facilitating long-term bilateral contracts between large loads and generators.


Together these shift more of the resource-adequacy function toward contracted structures — executed interconnection agreements and long-term offtake — and away from the auction clear.

Comments


© 2026 Simcore Partners LLC, including its subsidiaries and affiliates, is a consulting firm and not a certified public accounting firm or a law firm. All Rights Reserved.

Monthly Newsletter

Sign up for energy industry updates and analysis.

Thanks for submitting!

  • X
  • Instagram
  • LinkedIn
bottom of page