H1 2026 U.S. Power Market Update: Regional Responses to Rising Electricity Demand
- Jul 8
- 6 min read
In H1 2026, one theme came to define U.S. power markets: reallocation. As AI and data-center demand outpaced a delivery-constrained grid, the year turned less on adding capacity than on redirecting it — who pays for reliability, what provides it, and where the grid gets built next.
PJM
A capacity shortfall, a record grid bill, and a $67B merger
PJM's capacity market reached its limits in H1 2026. The 2027/28 capacity auction cleared at its price cap yet still recorded the first RTO-wide capacity shortfall, driven by rising demand rather than generation retirements. As a result, the cost of maintaining reliability is increasingly shifting beyond the capacity market and into transmission investments and large-load cost recovery.

KEY DEVELOPMENTS:
The 2027/28 Base Residual Auction (results Dec 2025) cleared at its $333.44/MW-day cap yet still fell 6,623 MW short — PJM's first RTO-wide shortfall, at a record-low ~15% reserve margin. Forecast peak load for 2027/28 rose to about 164.6 GW — up ~5,250 MW from ~159.3 GW in the prior auction — and PJM attributes roughly 5,100 MW of that increase to data centers; total cleared capacity payments reach about $16.4B.
To build out of the constraint, the Board approved an $11.8B RTEP — its largest ever — including ~$4.8B to Dominion (its total award across multiple projects), led by a 525-kV underground HVDC line into Loudoun County and a new 765-kV line in Ohio. Socializing those costs faces state pushback.
On June 18, 2026, FERC issued §206 show-cause orders directing all six FERC-jurisdictional RTOs to revise their large-load tariffs within 60 days; PJM's behind-the-meter / co-located rewrite came earlier, in FERC's Dec. 18, 2025 order — together settling who pays for, and who can bypass, the grid.
On May 18, 2026, NextEra and Dominion agreed to a $67B all-stock combination (NextEra the acquirer) to fund AI-era load — but a $150M securities settlement over FPL political-spending allegations clouds approval at the Virginia SCC.
ERCOT
Solar overtakes coal, storage scales, and data centers must pay

ERCOT offers an early blueprint for the AI-load era. While utility-scale solar is projected to surpass coal generation for the first time in 2026 (78 vs. 60 TWh), natural gas remains the dominant source of electricity, supplying more than 40% of all generation. The more significant structural shift is SB6, which requires large-load customers to fund their own interconnection costs.
KEY DEVELOPMENTS:
Utility-scale solar generation is set to outproduce coal for the first time in 2026 per EIA STEO (78 vs. 60 TWh). Solar's share has climbed from 4% of the mix in 2021 to ~12% by 2025, and Texas now accounts for roughly 40% of all U.S. solar additions.
Solar growth has helped make ERCOT the largest U.S. battery market: ~20 GW (June 2026, up from ~14 GW in 2025), tracking toward ~37 GW by 2027 — with storage repeatedly carrying the evening peak and damping the price spikes that defined past summers.
SB 6 (enacted June 2025) makes loads ≥75 MW fund their own interconnection. The PUCT's draft rule would require a $50,000/MW security and 100% of interconnection costs upfront, and on June 18, 2026 — the same day as FERC's §206 order — the PUCT approved ERCOT's batched "Batch Zero" study process. Ahead of FERC’s order, Texas assigned large-load interconnection costs directly to the customer, unrecoverable through regulated rates.
Real-Time Co-Optimization plus Batteries (RTC+B), ERCOT's biggest market redesign since 2010, went live in December 2025 — co-optimizing energy and ancillaries every five minutes and modeling battery state-of-charge. This has reshaped how batteries earn revenues and how the system manages evening peaks.
MISO & CAISO
Two divergent bets: coal economics vs. a solar-led grid

Same demand pressure, opposite responses. MISO's coal fleet remained economically competitive amid elevated winter natural gas prices, while CAISO prioritized storage and grid-enhancing technologies over new transmission. Neither approach reflects technology preference; both are shaped by regional fuel economics and existing infrastructure.
KEY DEVELOPMENTS:
MISO — coal holds on economics
Coal stayed the most profitable fuel — a ~$28/MWh dark spread vs. ~$9 for gas (Jan–Apr 2026 avg) — after Winter Storm Fern drove gas-fired generation cost to a peak ~$549/MWh in late January (from ~$25/MWh a week earlier); on-site fuel is a physical hedge against winter gas volatility.
The 2026/27 auction was two-speed: annualized prices fell ~42% to ~$126/MW-day on a 4.6 GW surplus, but summer (Zones 1–7) cleared $424.30 — risk now concentrates in summer
The Board approved the $21.8B Tranche 2.1 portfolio (3,631 mi of 765/345-kV); five states have challenged the cost allocation at FERC.
CAISO — a leaner, load-serving grid
Utility-scale solar surpassed gas for the first time over Jan–May 2026, beating it on 82% of days (up from 21% in 2024–25) — making daytime-to-evening storage increasingly critical.
The $6.7B transmission plan (38 projects) was driven increasingly by load growth (upgrades near fast-growing demand centers) rather than connecting remote renewables.
CAISO canceled the Serrano–Del Amo– Mesa 500-kV line after its estimate rose from $1.2B to ~$5.0B, choosing an alternative to reconductor smaller lines + targeted energy storage.
Other Notable Developments
NYISO
Large-load interconnection requests jumped from 1,045 MW (2022) to 12,670 MW by May 2026
Power Trends 2026 warns margins are narrowing as retirements outpace supply.
ISO-NE
FCA 18 (2027/28) cleared at $3.58/kW-month — about $1 higher than the prior four auctions.
FERC approved Phase 1 of ISO-NE's Capacity Auction Reforms in March 2026 — a shift to a prompt, ~month-ahead auction. Winter fuel-security accreditation is Phase 2, not yet filed.
SPP
On April 1, 2026, SPP extended its RTO into the Western Interconnection — the first U.S. RTO to span both the Eastern and Western Interconnections.
Nine western utilities joined, gaining access to a broader resource portfolio and coordinated reliability services across a wider footprint.
Southeast
No organized market: utilities recover costs via IRPs, with large loads increasingly placed on minimum-bill and take-or-pay style tariffs.
Georgia Power (Dec 2025) adds ~10 GW (~$16B), ~80% data-center-driven; loads above 100 MW face 15-year minimum-bill deals.
Duke’s Carolinas plan carries ~14 GW of new build; its advanced-development large-load pipeline (mostly data centers) reached 5.6 GW across 38 projects, up from 1.4 GW in 2023.
TVA’s draft 2026 IRP weighs 7–26 GW of new gas by 2040; its board voted to keep Cumberland and Kingston coal units running past prior retirement dates.
Nuclear
Hyperscalers have announced ~13 GW of nuclear, but ~6.9 GW is likely to materialize by the early 2030s (Carnegie, 2026).
Meta’s 6.6 GW package (Jan 2026) pairs existing plants with SMRs, majority into PJM.
Nuclear PPAs near ~$100–115/MWh sit above merchant; restarts still face timing risk, with Crane (TMI-1) targeting 2H 2027.
Takeaways
Interconnection is the binding constraint. FERC's §206 order rewrites large-load rules, and an executed Interconnection Agreement (IA) is now the gate to financing — no IA, no non-recourse debt. With grid access scarce, some large loads go behind-the-meter to secure power while staying grid-connected.
The ITC begin-construction window has now closed. Wind and solar that missed the July 4 start must now reach service by end-2027 — so underwriting shifts to safe-harbor proof and COD certainty. A June 6 ruling restored the 5% safe harbor (subject to appeal). Overall, solar and wind have now overtaken coal generation.
Demand remains a thesis, not a given. In the U.S., the majority of data center capacity is still in the announced or early development stage with a fraction of projects operating or under construction. Sightline Climate estimates that ~30–50% of planned capacity could be delayed or canceled. The queue signals intent, not committed demand.
Looking Ahead
Jul 2026 | PJM's 2028/29 auction results (Jul 14) test whether the shortfall repeats. |
Aug 2026 | Six RTOs file show-cause and tariff responses (Aug 17; adequacy reports Jul 20), shaping who funds interconnection. |
Dec 2026 | PUCT finalizes Texas SB6; PJM’s 2029/30 auction runs; MISO’s $21.8B Tranche 2.1 allocation stays contested at FERC. |
Winter 2026–27 | NYISO and ISO-NE capacity redesigns face their first winter. Tight margins would invite NERC alerts and fresh market reform. FEOC content step-up — foreign-content thresholds ratchet (~40→45%); sourcing becomes a credit-eligibility gate. |
H2 2027 | Crane (TMI-1) restarts target 2H 2027; Palisades already slipped. On-schedule nuclear sets the price floor for firm AI load. NextEra–Dominion close — $67B merger (largest US regulated utility) pending FERC / NRC / state review — watch the FERC filing as the trigger. |
End-2027 | U.S. projects without a durable BOC position face a 2027 ITC in-service deadline — even though only a fraction of announced data-center capacity is under construction. |




Comments